The three equal winners of the design competition participated in a negotiated procedure without publication.
The negotiated procedure was carried out in the form of confidential, parallel negotiations between the contracting authority and the individual winners of the design competition.
The three teams participating were:
schmidt hammer lassen architects, Arkitekt Kristine Jensens Tegnestue aps, ALECTIA A/S, Bosch & Fjord aps, Bibliotekskonsulenter Henrik Jochumsen and Casper Hvenegaard Rasmussen
AART a/s, Arkitema K/S, Bascon A/S, COWI A/S, Prof. Niels Ole Finnemann, Peter Dreyer/Seismonaut, Lennart Bjørneborn/Danmarks Biblioteksskole, Hans Peter Kuhn
Mecanoo architecten, Gjørtz, Pank & Partnere A/S and NIRAS
The negotiated procedure took place from September 2008 until February 2009. In an intense proces of dialogue and negotiation all three projects were continously developed throughout the proces.
The negotiations have been carried out as both central meetings with a joint negotiation group as well as de-centralized meetings in smaller fora focusing on the following themes:
Theme 1: • Architecture, functionality, materials • Urban space, harbour square, traffic Theme 2: • Constructions, foundations • Technical installations, energy, sustainability, indoor climate Theme 3: • Development proces, citizen- and user involvement, CV's and co-operation • Contract Theme 4: • Economy
Read the evaluation report (in Danish) |